The City has completed the detailed design of the Hutton Street extension through to Walters Drive (Stage 1) and is progressing planning and procurement for construction.
Background
On 5 January 2018, Amendment 1291/41 to the Metropolitan Region Scheme was gazetted which reserved land for an extension of Hutton Street from Scarborough Beach Road through to Jon Sanders Drive.
The City undertook an investigation into the feasibility of extending the road in either one stage directly to Jon Sanders Drive, or in two stages being initially to Walters Drive and then finally to Jon Sanders Drive. The Western Australian Planning Commission also acquired the land required for the extension to Walters Drive.
The extension of Hutton Street aims to improve traffic flow in the area by reducing congestion on Scarborough Beach Road and other roads in the immediate network. Hutton Street will play an increasingly important role in the transportation of freight between Osborne Park and the broader region.
In June 2024, the road south of Scarborough Beach Road was renamed Mineral Road. Please refer to the map below for the extent of Mineral Road.
Project update (May 2026)
The detailed design for Stage 1 has now been completed and was endorsed by Main Roads Western Australia (MRWA) through the Traffic Signal Approval Policy (TSAP) process.
The City is progressing procurement for construction while awaiting the outcome of the funding application through the MRWA’s Metropolitan Regional Road Group (MRRG) process, expected in July 2026.
The timing for construction and opening of the road remains subject to funding contributions from the State Government.
Project timeline
August 2023
Start of concept designs and option selection process
July 2024
Demolition works completed
August 2024
Feature and Utilities Surveys completed
August 2024
Start of detail design for the preferred option
March 2025
15% design endorsed by MRWA
May 2025
85% design accepted by the City and funding application submitted to MRWA
December 2025
100% design complete
July 2026
MRWA’s decision about City’s funding application
2026
Construction procurement (tender process)
2027
Construction starts, subject to successful state funding contributions for the project
2028
Road opens