Hutton Street Extension

Hutton Street Extension
  • Open date

    02 October 2024

Last update date: 28 July 2025

The City is currently designing the extension of Hutton Street through to Walters Drive. 

Background

On 5 January 2018, Amendment 1291/41 to the Metropolitan Region Scheme was gazetted which reserved land for an extension of Hutton Street from Scarborough Beach Road through to Jon Sanders Drive.

The City undertook investigation into the feasibility of extending the road in either one stage directly to Jon Sanders Drive, or in two stages being initially to Walters Drive and then finally to Jon Sanders Drive. The Western Australian Planning Commission has recently acquired the land required for the extension to Walters Drive.

The extension of Hutton Street aims to improve traffic flow in the area by reducing congestion on Scarborough Beach Road and other roads in the immediate network. Hutton Street will play an increasingly important role in the transportation of freight between Osborne Park and broader region.

In June 2024, the road south of Scarborough Beach Road was named Mineral Road. Please refer to the map below for the extent of Mineral Road.

Project update (June 2025)

The detailed design of the Hutton Street extension has achieved the 85% design milestone. The earlier 15% design was endorsed by Main Roads Western Australia (MRWA) as part of the Traffic Signal Approval Policy (TSAP) Stage 2. The 85% design has since been accepted by the City, and a funding application has been submitted to MRWA.

Once the 100% detailed design is completed, it will be submitted to MRWA for TSAP Stage 3. Following all necessary approvals, the design will be Issued for Construction (IFC).

The timing for construction and opening of the road remains subject to funding contributions from the State Government.

Project timeline

August 2023

Start of concept designs and option selection process

July 2024

Demolition works completed

August 2024

Feature and Utilities Surveys completed

August 2024

Start of detail design for the preferred option

March 2025

15% design endorsed by MRWA

May 2025

85% design accepted by the City and funding application submitted to MRWA

December 2025

MRWA’s decision about City’s funding application

End of 2026

Construction starts, subject to successful state funding contributions for the project

End of 2027

Road opens