Water Corporation Pipes for Perth - Beaufort Street 2022

In 2022, Water Corporation will renew 2.1km of cast iron water pipeline along Beaufort Street, between Walcott Street, Mt Lawley and Dundas Road, Inglewood in the City of Stirling. Follow project

The City is supporting Water Corporation in the delivery of 2.1kms of new water main on Beaufort Street, between Walcott Street, Mt Lawley and Dundas Road in Inglewood. 

FAQs

What exactly will be taking place?

The Water Corporation will be replacing cast iron pipes that are over 100 years old with PVC. Works will be carried out in a staged approach within the Beaufort Street northbound traffic lanes, which will be closed to road users during construction. The Water Corporation is working with the City of Stirling, Main Roads and the Public Transport Authority on important project detail including traffic management.

Why does the northbound traffic lane need to be closed?

The width of the road does not allow for safe contra-flow traffic arrangements, meaning the northbound lane will be closed and traffic will be detoured in stages. 

How will the works be staged?

There will be three stages of works (Walcott Street to First Avenue, First Avenue to Central Avenue and Central Avenue to Dundas Road). Each stage will take about 8 weeks to complete with two crews per stage.  The order of staging is yet to be determined.

How long will the works take?

Construction will take place from May 2022 to October/November 2022.

How will businesses be supported during this time?

Water Corporation will work closely with the local business community leading up and during construction to mitigate impacts, where practically possible.

Where can I provide my feedback?

The City of Stirling is supporting the Water Corporation to deliver this critical project. All feedback can be provided here: https://yoursay.watercorporation.com.au/beaufort-street   

How can I keep updated with the project?

Timeline

Pre construction timeline

August 2021 - April 2022

Stage 1 construction

May to June 2022

Stage 2 construction

July to August 2022

Stage 3 construction

September to October 2022

Contingency

November 2022