Construction Works Progress - Princess Wallington Community Parkland

22 May 2020

Works are progressing on site with notable milestones reached in May 2020 including;

  • Junior and Advanced BMX tracks complete
  • Balga Soccer Club sewer connection complete
  • Playground equipment structures in place (flying fox, swing set, nest swing)
  • Playground paths installed
  • Ablution block structure in place (Universal accessible toilet and ambulant toilet
  • Management of asbestos affected soil.

For more information, return to the Princess Wallington Community Parkland page.